Caserones Copper Outage Hits Chile Mine, Lundin Keeps Target

riotimesonline.com · 13d

How the coverage leans

Across 3 sources · syndicated copies counted once

Chile · Mining Key Facts —Cause. A severe winter storm in the Atacama Region damaged two transmission towers, cutting grid power to the Caserones mine on 18 July 2026. —Duration. Lundin Mining expects a total power restoration and gradual restart within two to three weeks from its 27 July update. —Production. Analysts estimate the outage […] The post Caserones Copper Outage Hits Chile Mine, Lundin Keeps Target appeared first on The Rio Times .

First report: Lundin Says Chile Mine Restart After Storm May Take 2-3 Weeks bloomberg.com, 15d

The coverage

  1. Lundin Mining says Chilean mine restart to take 2-3 weeks after winter storm